Schedule
| Notice of Preparation/Notice of Intent | June 27, 2008 |
| Public Scoping Meeting | July 29, 2008 |
| Prepare Technical Reports and the Draft EIR/EIS | Spring 2009 |
| Draft EIR/EIS Circulation and Start of Public Comment Period | May 20, 2011 |
| Public Hearing on Draft EIR/EIS | June 9, 2011 |
| End of Public Comment Period | July 11, 2011 |
| Preferred Alternative 2 Selected | September 20, 2011 |
| Final Environmental Document and Record of Decision by Caltrans | Mid 2012 |
| Award Design-Build Contract | 2013 |
| New Lanes Open | 2017 |